Pizza Hut Park progress report

Pizza Hut Park will definitely open on August 6, 2005 when FC Dallas hosts the MetroStars. The 21,193-seat soccer specific stadium and the 17 regulation-sized, tournament-grade soccer fields to the north are still a work in progress as the facility is now 45 days away from its opening.


This Pizza Hut Park Progress Report is meant to update the public on the status of the facility leading up to Opening Day. The report will be sent out bi-weekly with facts and figures regarding Pizza Hut Park and how the construction on the 117-acre complex is heading towards completion in several key categories. Each report will have a few important categories and their present status.


FACILITY CATEGORY FACT PERCENT COMPLETED Sidewalks for facility 12,500 linear feet 80% Irrigation piping for facility 46,000 linear feet 90% Sprinkler Heads at facility 950 total 85%

On Monday, June 27 the progress report will shift its focus to the soccer stadium at Pizza Hut Park which will be ready for a Major League Soccer match on August 6, 2005.